Government officials will NEVER ask you to transfer money or disclose bank log-in details over a phone call. Call the 24/7 ScamShield Helpline at 1799 if you are unsure if something is a scam. For details, visit the ScamShield website.
SCDF does not endorse or certify products. Legitimate fire safety products are certified by independent accredited Certification Bodies. Claims of 'SCDF-approved' or similar are false. Report them at https://www.scdf.gov.sg/home/feedback.
With effect from 21 Dec 2026, the SCDF Hotline (1800 280 0000) will cease operations. For emergencies, please call 995 or SMS to 70995. For non-emergencies, please contact us via the SCDF Feedback Form.
The application for Registered Inspector (RI) is open from 1 Nov to 30 Nov 2026. Please download the application form at https://www.scdf.gov.sg/fire-safety-services-listing/downloads/forms-and-guides.

1

/

4

Search TRHS
Include in Search
Clear All

Finishes within a HS shall comply with the following:

a. The walls and the ceiling slab shall be cast with a smooth concrete finish.

b. The walls and ceiling slab may be finished with a skim coat of not thicker than 2mm.

c. No plastering or tiling shall be permitted on the walls and ceiling slab.

d. Floor tiles or floor finishes, which are laid on wet cement mortar, are permitted.

e. Skirting tiles laid on wet cement mortar are permitted up to a maximum 100mm high above the FFL.