Maintenance Notice: The SCDF website will be undergoing a system upgrade on 15 October 2026, from 7pm to 10pm. Users may experience intermittent downtime during this period. We apologise in advance for any inconvenience caused.
Please be informed that Alexandra Fire Station will not be hosting the weekly Saturday Fire Station Open House on 17 October 2026. Please refer to the list of other Fire Stations that are available for visits.
Government officials will NEVER ask you to transfer money or disclose bank log-in details over a phone call. Call the 24/7 ScamShield Helpline at 1799 if you are unsure if something is a scam. For details, visit the ScamShield website.
Please be informed that Yishun Fire Station will not be hosting the weekly Saturday Fire Station Open House from 28 February 2026 to March 2028. Please refer to the list of other Fire Stations that are available for visits.
SCDF does not endorse or certify products. Legitimate fire safety products are certified by independent accredited Certification Bodies. Claims of 'SCDF-approved' or similar are false. Report them at https://www.scdf.gov.sg/home/feedback.
The application for Registered Inspector (RI) is open from 1 Nov to 30 Nov 2026. Please download the application form at https://www.scdf.gov.sg/fire-safety-services-listing/downloads/forms-and-guides.

1

/

6

Search TRHS
Include in Search
Clear All

Finishes within a HS shall comply with the following:

a. The walls and the ceiling slab shall be cast with a smooth concrete finish.

b. The walls and ceiling slab may be finished with a skim coat of not thicker than 2mm.

c. No plastering or tiling shall be permitted on the walls and ceiling slab.

d. Floor tiles or floor finishes, which are laid on wet cement mortar, are permitted.

e. Skirting tiles laid on wet cement mortar are permitted up to a maximum 100mm high above the FFL.