Please be informed that Yishun Fire Station will not be hosting the weekly Saturday Fire Station Open House from 28 February 2026 to March 2028. Please refer to the list of other Fire Stations that are available for visits.
Government officials will NEVER ask you to transfer money or disclose bank log-in details over a phone call. Call the 24/7 ScamShield Helpline at 1799 if you are unsure if something is a scam. For details, visit the ScamShield website.
Please be informed that Central Fire Station will not be hosting the weekly Saturday Fire Station Open House on 10 October 2026. Please refer to the list of other Fire Stations that are available for visits.
Please be informed that Marina Bay Fire Station will not be hosting the weekly Saturday Fire Station Open House until further notice. Please refer to the list of other Fire Stations that are available for visits.

1

/

4

Performance-Based Provisions Code Structure

The performance-based provisions in the revised Fire Code are structured according to the following format:

(i) Root objectives

Root objectives spell out the intents of the Fire Code.

(ii) Sub-objectives

Sub-objectives define the conditions to fulfil the intents as spelt out in the root objectives.

Under the performance-based regulatory system, there can be 3 approaches to the design of fire safety works:

(i) Performance-based approach

(ii) Prescriptive (Deemed-to-satisfy) approach*

(iii) Hybrid of performance-based and prescriptive approach

* Prescriptive requirements of the Fire Code are known as 'deemed-to-satisfy' requirements in the performance-based regulatory system.

Figure 1: Flowchart illustrating the 3 approaches to design of fire safety works