Fire Safety

Quantitative Risk Assessment (QRA) Requirements

Risk Assessment for Transport/Handle/Storage of Petroleum and Flammable Materials (P&FM) in Singapore

Under the Fire Safety (Petroleum and Flammable Materials) Regulations, SCDF may request any new or existing premises undergoing modifications/expansions and transporting/handing/storing (ie. road transportation, pipelines, fixed installations) large quantities of petroleum and flammable materials to carry out a quantitative risk assessment (QRA) study. Please refer to http://www.nea.gov.sg/anti-pollution-radiation-protection/central-building-planning for the QRA Technical Guidance

Objectives of QRA

The objectives of QRA are:

  • To identify hazards and quantify the risks related to the transport, handle and storage of P&FM;
  • To recommend practical measures to reduce the hazards and risks to as low as reasonably practicable;
  • To establish (where applicable) Health & Safety (H&S) buffers to guide land use planning; and
  • To use for information sharing and emergency planning purposes.

QRA Criteria

The revised QRA guidelines has taken effect since 1 Apr 2016. It is a risk based methodology benchmarked against international best practices. The methodology has gone through extensive industry consultation and obtained buy in before its official implementation. Please refer to http://www.nea.gov.sg/anti-pollution-radiation-protection/central-building-planning for the QRA guidelines criteria.

QRA Work Process

The Major Hazard Department (MHD) is an inter-agency (MOM/NEA/SCDF) regulatory office that has been set up in MOM since 1 September 2016 to implement the Safety Case Regime. It would also act as a single regulatory front to handle and coordinate all QRA submissions.

 

The responsible party is advised to approach MHD (CONTACT_MHD@mom.gov.sg) at the earliest possible time (e.g. basic concept and design stage / pre-Front End Engineering Design (FEED) stage) for pre-consultations (e.g. need for QRA study, expected timeline) and clarifications, to facilitate the QRA assessment process. The responsible party is requested to submit the QRA pre-consultation form when they approach MHD. Please refer to Appendix A for the QRA pre-consultation form template.

 

If a QRA study is required, the responsible party is to engage a registered QRA consultant to carry out the QRA study. The QRA report would be evaluated by a multi-agency (SCDF/NEA/MOM/URA/JTC/SPF) committee. Any findings and recommendations from the QRA report pertaining to fire safety provisions shall be adequately addressed in the fire safety plan submission. The responsible party shall obtain the in-principle no objection to the QRA report before any commencement of works. Please refer to http://www.nea.gov.sg/anti-pollution-radiation-protection/central-building-planning for the list of registered QRA consultants. Please refer to Appendix B for the key regulatory control cycle for the transport/handle/storage of P&FM in Singapore.


 

back to top

Last updated on 6th Mar 2017