Who require plan approval?

 
 

Any person who wishes to commence or carry out any proposed fire safety works in any building shall apply in accordance with the Regulations made under the Fire Safety Act to the Fire Safety and Shelter Department (FSSD) for approval of the plans of the fire safety works. Such plans shall be prepared and submitted by Qualified Persons (QPs) who are registered architects or professional engineers.

 
     
 

Who are qualified for submission of plans?

 
 

Click on the following links for the list of Registered Architects (RA) and Professional Engineers (PE):

QPs with the discipline relevant to the kind of work involved is qualified for making plan submission.

Click on the link to know the Relevant Qualified Persons for Building Plans, Fire Protection and Mechanical Ventilation Plans to be submitted under Section 23 of the Fire Safety Act.
(pdf 1.16MB)

Click on the link to know the Relevant Qualified Persons and Registered Inspectors for Submissons of Plans on Combustible Gas / Hazardous Material Installation. (pdf162KB)

 
     
 

What are the accepted Code of Practice?

 
 

Accepted Codes of Practice for various types of plan submissions (Word 30KB)

 
     
     
 

Submission Procedures for the following plans

 
 

a) Manual Submission

 
 

The QP or his / her representative should make the plan submission in person.

 
     
 

** Click on the hyperlink to find out the necessary documents required for submission.
1) Building Plans
2) Air-Conditioning & Mechanical Ventilation Plan
3) Fire Protection Plan
4) Change of Use

 
     
 

b) Electronic Submission

 
     
     
 

The following are required for the different types of plan submission:

 
 

1) Submission Requirements for Building Plans

 
 

• One set of plan;
• Application form FSSD-PA;
• Plan fees;
• QP's declaration form;
• Occupancy load calculations and unprotected opening calculations, where applicable;
• Other supporting documents if any.

 
     
 

All plans, calculations, QP's report and application form shall be signed by the QP. All plans shall be of standard metric 'A' series sizes.

 
     
     
 

2) Submission Requirements for Air Conditioning & Mechanical Ventilation Plan

 
 

• One set of plan;
• Application form FSSD-PA;
• Plan fees;
• QP's declaration form;
•Pressurization staircase calculations and smoke control calculations where applicable;
• Other supporting documents if any.

 
     
 

All plans, calculations, QP's report and application form shall be signed by the QP. All plans shall be of standard metric 'A' series sizes.

 
     
     
 

3) Submission Requirements for Fire Protection Plan

 
 

• One set of plan;
• Application form FSSD-PA;
• Plan fees;
• QP's declaration form;
• Sprinkler hydraulic calculations where applicable;
• Other supporting documents if any.

 
 
 
 

All plans, calculations, QP's report and application form shall be signed by the QP.
All plans shall be of standard metric 'A' series sizes.

 
     
     
 

4) Submission Requirements for Change of Use

 
 

A change of use application shall be incorporated in the building plan submission.
QP is required to specify clearly in the project titles on plans and in the application forms the proposed intention of the change of use. No separate submission is required.

 
     
 

**NOTE: Fire Safety Works do not require submission to SCDF

 
 

Under the Exemption Order of the Fire Safety Act, the following fire safety works which are installed in the building works do not require submission to Fire Safety & Shelter Department:

Fire Safety Exemption Order document (PDF, 82 KB)

 
     
 